Total Documents

242

Tracked in MDR

Timeline Duration

99 days

Total span

Earliest Start

2025-10-06

Dataset baseline

Latest Finish

2026-01-12

Projected completion

Schedule Items

7 tasks displayed

Categories tracked: 18
ID Name Category Status Start Finish Duration (d) Budgeted Units Actions
ARLNG-019-FEL2-PBO-1000-ELE-RPT-0001 Electrical studies (power source and availability) ELE Not issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1002-ELE-LST-0003 Electrical load list and load balance (Compressor Station) ELE Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1032-ELE-LST-0002 Electrical load list and load balance (Central Hub) ELE Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-ELE-LST-0001 Electrical load list and load balance (BVS, scraper trap stations) ELE Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-ELE-SLD-0003 Single-line diagrams (Compression station) ELE Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-ELE-SLD-0002 Single-line diagrams (Cental Hub) ELE Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-ELE-SLD-0001 Single-line diagrams (BVS, scraper trap stations) ELE Issued 2025-12-19 2025-12-19 1 0