Total Documents
242
Tracked in MDR
Timeline Duration
99 days
Total span
Earliest Start
2025-10-06
Dataset baseline
Latest Finish
2026-01-12
Projected completion
All Disciplines
242
Architectural (ARC)
6
Commissioning (CMM)
1
Construction (CON)
3
Civil (CVS)
10
Electrical (ELE)
7
HSSE (Health, Safety, Security and Environment) (HSE)
2
INS
6
Piping (PIP)
5
Pipelines and Flow lines (PLF)
135
Project Planning (PLG)
3
Project Management (PMG)
7
PMT
7
Process (PRO)
29
Process Safety Management (PSM)
7
Quality Assurance & Control (QAC)
1
Mechanical Rotating (ROT)
7
Mechanical Static (STA)
4
Structural (STC)
2
Issued · 4
Not issued · 3
Schedule Items
7 tasks displayed
Categories tracked: 18
| ID | Name | Category | Status | Start | Finish | Duration (d) | Budgeted Units | Actions |
|---|---|---|---|---|---|---|---|---|
| ARLNG-019-FEL2-PBO-1000-PMT-LST-0001 | Light FEED Master Deliverables List (MDL) | PMT | Issued | 2025-10-17 | 2025-10-17 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PMT-PLN-0001 | Light FEED PEP (Project Execution Plan) | PMT | Issued | 2025-10-31 | 2025-10-31 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PMT-RPT-0001 | Light FEED Close-out Report | PMT | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PMT-SOW-0001 | EPC Scope of Works | PMT | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PMT-PLN-0002 | PEP EPC Phase | PMT | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PMT-BFD-0001 | Light FEED Block diagram | PMT | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PMT-CAL-0001 | Light FEED Descriptive memory | PMT | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 |