Total Documents
242
Tracked in MDR
Timeline Duration
99 days
Total span
Earliest Start
2025-10-06
Dataset baseline
Latest Finish
2026-01-12
Projected completion
All Disciplines
242
Architectural (ARC)
6
Commissioning (CMM)
1
Construction (CON)
3
Civil (CVS)
10
Electrical (ELE)
7
HSSE (Health, Safety, Security and Environment) (HSE)
2
INS
6
Piping (PIP)
5
Pipelines and Flow lines (PLF)
135
Project Planning (PLG)
3
Project Management (PMG)
7
PMT
7
Process (PRO)
29
Process Safety Management (PSM)
7
Quality Assurance & Control (QAC)
1
Mechanical Rotating (ROT)
7
Mechanical Static (STA)
4
Structural (STC)
2
Not issued · 7
Issued · 22
Schedule Items
29 tasks displayed
Categories tracked: 18
| ID | Name | Category | Status | Start | Finish | Duration (d) | Budgeted Units | Actions |
|---|---|---|---|---|---|---|---|---|
| ARLNG-019-FEL2-PBO-1000-PRO-PLN-0001 | Procurement Plan for EPC phase | PRO | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PRO-DES-0001 | EPC Basis of Design | PRO | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PRO-DES-0002 | LIGHT FEED Basis of Design for all disciplines | PRO | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-RPT-0001 | Hydraulic Calculations Report | PRO | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PRO-PFD-0002 | Process Flow Diagrams and H&MB (Compression station) | PRO | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-PFD-0001 | Process Flow Diagrams and H&MB (Central Hub) | PRO | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-UFD-0002 | Utilities Flow Diagrams (Compression station) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-UFD-0001 | Utilities Flow Diagrams (Central Hub) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-PID-0003 | Piping & Instrument Diagrams (Compression station) | PRO | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-PID-0002 | Piping & Instrument Diagrams (Central Hub) | PRO | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PRO-PID-0001 | Piping & Instrument Diagrams (BVS, Scraper trap stations) | PRO | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-RPT-0005 | Process Equipment Summary (Compressor Station) | PRO | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-RPT-0004 | Process Equipment Summary (Central Hub) | PRO | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-TDS-0002 | Datasheet for GAS SRUBBERS (Compressor Station) | PRO | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-TDS-0001 | Datasheet for AIRCOOLERS (Compressor Station) | PRO | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-TDS-0003 | Datasheet for STORAGE TANKS (Central Hub) | PRO | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-TDS-0004 | Datasheet for TURBOCOMPRESSORS (Compressor Station) | PRO | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-CAL-0002 | Process Equipment Calculation Note (Compressor Station) | PRO | Not issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-CAL-0001 | Process Equipment Calculation Note (Central Hub) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-RPT-0003 | Pressure relieving system calculation report (Compressor Station) | PRO | Not issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-RPT-0002 | Pressure relieving system calculation report (Central Hub) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-STR-0002 | Operation and Control Philosophy (Compressor Station) | PRO | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-STR-0001 | Operation and Control Philosophy (Central Hub) | PRO | Issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-TDS-0001 | Datasheet for MAIN PUMPS (Central Hub) | PRO | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-LST-0001 | Utilities Summary (Compressor Station) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-LST-0001 | Utilities Summary (Central Hub) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PRO-RPT-0001 | ALARP Demonstration | PRO | Not issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1002-PRO-LST-0003 | Effluent and Emission Summary (Compressor Station) | PRO | Not issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PRO-LST-0003 | Effluent and Emission Summary (Central Hub) | PRO | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 |