Total Documents

242

Tracked in MDR

Timeline Duration

99 days

Total span

Earliest Start

2025-10-06

Dataset baseline

Latest Finish

2026-01-12

Projected completion

Schedule Items

6 tasks displayed

Categories tracked: 18
ID Name Category Status Start Finish Duration (d) Budgeted Units Actions
ARLNG-019-FEL2-PBO-1000-INS-DWG-0003 Telecom and Security System Architecture (Overall) INS Issued 2025-11-28 2025-11-28 1 0
ARLNG-019-FEL2-PBO-1002-INS-DWG-0002 Control system architecture, safety, F&G and other systems (Compressor Station) INS Issued 2025-11-28 2025-11-28 1 0
ARLNG-019-FEL2-PBO-1032-INS-DWG-0001 Control system architecture, safety, F&G and other systems (Central Hub) INS Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-INS-SPC-0002 Technical Specification of Integrated Control and Safety System (ICSS) Design (Including DCS, SIS and FGS) INS Issued 2025-11-28 2025-11-28 1 0
ARLNG-019-FEL2-PBO-1000-INS-SPC-0001 Technical Specification of Custody Metering INS Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-INS-SPC-0003 Technical Specification for Telecom and Security System INS Issued 2025-11-18 2025-11-18 1 0