Total Documents
242
Tracked in MDR
Timeline Duration
99 days
Total span
Earliest Start
2025-10-06
Dataset baseline
Latest Finish
2026-01-12
Projected completion
All Disciplines
242
Architectural (ARC)
6
Commissioning (CMM)
1
Construction (CON)
3
Civil (CVS)
10
Electrical (ELE)
7
HSSE (Health, Safety, Security and Environment) (HSE)
2
INS
6
Piping (PIP)
5
Pipelines and Flow lines (PLF)
135
Project Planning (PLG)
3
Project Management (PMG)
7
PMT
7
Process (PRO)
29
Process Safety Management (PSM)
7
Quality Assurance & Control (QAC)
1
Mechanical Rotating (ROT)
7
Mechanical Static (STA)
4
Structural (STC)
2
Issued · 87
Not issued · 48
Schedule Items
135 tasks displayed
Categories tracked: 18
| ID | Name | Category | Status | Start | Finish | Duration (d) | Budgeted Units | Actions |
|---|---|---|---|---|---|---|---|---|
| ARLNG-019-FEL2-PBO-1000-PLF-STR-0001 | Material selection philosophy | PLF | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-SPC-0007 | Specification for pipeline valves | PLF | Issued | 2025-12-19 | 2025-12-19 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-DGM-0001 | Overall Pipeline schematic diagram | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-DES-0001 | Design Criteria for pipelines | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-DES-0002 | Pipeline Cathodic Protection Basis of Design | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-RPT-0003 | Pipelines Thickness Calculation and Selection Report | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-RPT-0001 | Buoyancy Calculation Report | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-PLN-0001 | Overall Pipelines Route Plan | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-RPT-0002 | Special Crossings Design report | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-CRS-0002 | Gas Pipeline - Limay River Crossing Detail | PLF | Issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-CRS-0003 | Gas Pipeline - State Road 22 and Channel Crossing Detail | PLF | Issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-CRS-0001 | C3+ & C2 Pipelines - Nequen River Crossing Detail | PLF | Issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-LST-0001 | Pipeline Crossings List | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-MTO-0001 | Material Take Off Pipeline | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-SPC-0002 | Line Pipe Technical Specification | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-SPC-0004 | Specification for hot induction bends | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-SPC-0006 | Specification for Pipeline Monolothic Isolation Joint | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-SPC-0005 | Specification for Pipeline Flanges & Fittings (Barred TEEs) | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-SPC-0001 | Line Pipe External Coating and Internal Flow Coating Technical Specification | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-0000-PLF-SPC-0003 | Pipeline Field Joint Coating Specification | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0007 | Typical Pipeline RoW Cross Sections | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-DWG-0009 | Typical Pipeline Trench Drawing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0011 | Typical Watercourse Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0005 | Typical Channel Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0008 | Typical Railway Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0009 | Typical State and Provincial Roads Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0010 | Typical Unpaved Road Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0004 | Typical Buried Pipe and Cable Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-CRS-0006 | Typical O/h Power Line Crossing | PLF | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0001 | ALIGNMENT SHEET GAS PIPELINE FROM 0+000 TO 9+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0002 | ALIGNMENT SHEET GAS PIPELINE FROM 9+000 TO 19+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0003 | ALIGNMENT SHEET GAS PIPELINE FROM 19+000 TO 29+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0004 | ALIGNMENT SHEET GAS PIPELINE FROM 29+000 TO 39+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0005 | ALIGNMENT SHEET GAS PIPELINE FROM 39+000 TO 49+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0006 | ALIGNMENT SHEET GAS PIPELINE FROM 49+000 TO 59+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0007 | ALIGNMENT SHEET GAS PIPELINE FROM 59+000 TO 69+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0008 | ALIGNMENT SHEET GAS PIPELINE FROM 69+000 TO 79+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0010 | ALIGNMENT SHEET GAS PIPELINE FROM 79+000 TO 89+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0011 | ALIGNMENT SHEET GAS PIPELINE FROM 89+000 TO 99+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0012 | ALIGNMENT SHEET GAS PIPELINE FROM 99+000 TO 109+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0013 | ALIGNMENT SHEET GAS PIPELINE FROM 109+000 TO 119+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0014 | ALIGNMENT SHEET GAS PIPELINE FROM 119+000 TO 129+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0015 | ALIGNMENT SHEET GAS PIPELINE FROM 129+000 TO 139+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0016 | ALIGNMENT SHEET GAS PIPELINE FROM 139+000 TO 149+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0017 | ALIGNMENT SHEET GAS PIPELINE FROM 149+000 TO 159+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0018 | ALIGNMENT SHEET GAS PIPELINE FROM 159+000 TO 169+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0019 | ALIGNMENT SHEET GAS PIPELINE FROM 169+000 TO 179+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0020 | ALIGNMENT SHEET GAS PIPELINE FROM 179+000 TO 189+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0021 | ALIGNMENT SHEET GAS PIPELINE FROM 189+000 TO 199+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0022 | ALIGNMENT SHEET GAS PIPELINE FROM 199+000 TO 209+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0023 | ALIGNMENT SHEET GAS PIPELINE FROM 209+000 TO 219+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0024 | ALIGNMENT SHEET GAS PIPELINE FROM 219+000 TO 229+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0025 | ALIGNMENT SHEET GAS PIPELINE FROM 229+000 TO 239+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0026 | ALIGNMENT SHEET GAS PIPELINE FROM 239+000 TO 249+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0027 | ALIGNMENT SHEET GAS PIPELINE FROM 249+000 TO 259+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0028 | ALIGNMENT SHEET GAS PIPELINE FROM 259+000 TO 269+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0029 | ALIGNMENT SHEET GAS PIPELINE FROM 269+000 TO 279+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0030 | ALIGNMENT SHEET GAS PIPELINE FROM 279+000 TO 289+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0031 | ALIGNMENT SHEET GAS PIPELINE FROM 289+000 TO 299+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0032 | ALIGNMENT SHEET GAS PIPELINE FROM 299+000 TO 309+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0033 | ALIGNMENT SHEET GAS PIPELINE FROM 309+000 TO 319+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0034 | ALIGNMENT SHEET GAS PIPELINE FROM 319+000 TO 329+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0035 | ALIGNMENT SHEET GAS PIPELINE FROM 329+000 TO 339+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0036 | ALIGNMENT SHEET GAS PIPELINE FROM 339+000 TO 349+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0037 | ALIGNMENT SHEET GAS PIPELINE FROM 349+000 TO 359+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0038 | ALIGNMENT SHEET GAS PIPELINE FROM 359+000 TO 369+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0039 | ALIGNMENT SHEET GAS PIPELINE FROM 369+000 TO 379+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0040 | ALIGNMENT SHEET GAS PIPELINE FROM 379+000 TO 389+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0041 | ALIGNMENT SHEET GAS PIPELINE FROM 389+000 TO 399+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0042 | ALIGNMENT SHEET GAS PIPELINE FROM 399+000 TO 409+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0043 | ALIGNMENT SHEET GAS PIPELINE FROM 409+000 TO 419+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0044 | ALIGNMENT SHEET GAS PIPELINE FROM 419+000 TO 429+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0045 | ALIGNMENT SHEET GAS PIPELINE FROM 429+000 TO 439+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0046 | ALIGNMENT SHEET GAS PIPELINE FROM 439+000 TO 449+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0047 | ALIGNMENT SHEET GAS PIPELINE FROM 449+000 TO 459+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0048 | ALIGNMENT SHEET GAS PIPELINE FROM 459+000 TO 469+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0049 | ALIGNMENT SHEET GAS PIPELINE FROM 469+000 TO 479+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0050 | ALIGNMENT SHEET GAS PIPELINE FROM 479+000 TO 489+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0051 | ALIGNMENT SHEET GAS PIPELINE FROM 489+000 TO 499+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0052 | ALIGNMENT SHEET GAS PIPELINE FROM 499+000 TO 509+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0053 | ALIGNMENT SHEET GAS PIPELINE FROM 509+000 TO 519+000 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1001-PLF-DWG-0054 | ALIGNMENT SHEET GAS PIPELINE FROM 519+000 TO 520+929 | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0055 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 0+000 TO 10+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0056 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 10+000 TO 20+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0057 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 20+000 TO 30+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0058 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 30+000 TO 40+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0059 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 40+000 TO 50+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0060 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 50+000 TO 60+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0061 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 60+000 TO 70+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0062 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 70+000 TO 80+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0063 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 80+000 TO 90+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0064 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 90+000 TO 100+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0065 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 100+000 TO 110+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0066 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 110+000 TO 120+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0067 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 120+000 TO 130+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0068 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 130+000 TO 140+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0069 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 140+000 TO 150+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0070 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 150+000 TO 160+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0071 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 160+000 TO 170+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0072 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 170+000 TO 180+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0073 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 180+000 TO 190+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0074 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 190+000 TO 200+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0075 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 200+000 TO 210+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0076 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 210+000 TO 220+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0077 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 220+000 TO 230+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0078 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 230+000 TO 240+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0079 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 240+000 TO 250+000 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1031-PLF-DWG-0080 | ALIGNMENT SHEET CONDENSATE PIPELINE FROM 250+000 TO 250+655 | PLF | Not issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1020-PLF-DWG-0081 | ALIGNMENT SHEET C3+ PIPELINE FROM 0+000 TO 10+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1020-PLF-DWG-0082 | ALIGNMENT SHEET C3+ PIPELINE FROM 10+000 TO 20+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1020-PLF-DWG-0083 | ALIGNMENT SHEET C3+ PIPELINE FROM 20+000 TO 30+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1020-PLF-DWG-0084 | ALIGNMENT SHEET C3+ PIPELINE FROM 30+000 TO 40+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1020-PLF-DWG-0085 | ALIGNMENT SHEET C3+ PIPELINE FROM 40+000 TO 42+662 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0086 | ALIGNMENT SHEET C2 PIPELINE FROM 0+000 TO 10+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0087 | ALIGNMENT SHEET C2 PIPELINE FROM 10+000 TO 20+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0088 | ALIGNMENT SHEET C2 PIPELINE FROM 20+000 TO 30+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0089 | ALIGNMENT SHEET C2 PIPELINE FROM 30+000 TO 40+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0090 | ALIGNMENT SHEET C2 PIPELINE FROM 40+000 TO 50+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0091 | ALIGNMENT SHEET C2 PIPELINE FROM 50+000 TO 60+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-0000-PLF-DWG-0092 | ALIGNMENT SHEET C2 PIPELINE FROM 60+000 TO 70+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0093 | ALIGNMENT SHEET C2 PIPELINE FROM 70+000 TO 80+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0094 | ALIGNMENT SHEET C2 PIPELINE FROM 80+000 TO 90+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0095 | ALIGNMENT SHEET C2 PIPELINE FROM 90+000 TO 100+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0096 | ALIGNMENT SHEET C2 PIPELINE FROM 100+000 TO 110+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0097 | ALIGNMENT SHEET C2 PIPELINE FROM 110+000 TO 120+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0098 | ALIGNMENT SHEET C2 PIPELINE FROM 120+000 TO 130+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0099 | ALIGNMENT SHEET C2 PIPELINE FROM 130+000 TO 140+000 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1010-PLF-DWG-0100 | ALIGNMENT SHEET C2 PIPELINE FROM 140+000 TO 149+892 | PLF | Not issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-DWG-0001 | Geographic base for pipeline design (Kmz) | PLF | Issued | 2026-01-12 | 2026-01-12 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-MRE-0001 | Material Requisition for Pipeline Valves | PLF | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-MRE-0003 | Material Requisition for Line Pipe | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-MRE-0005 | Material Requisition for Hot Induced Bend | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-MRE-0007 | Material Requisition for Barred TEE | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-MRE-0009 | Material Requisition for Insulation Joint | PLF | Issued | 2025-11-28 | 2025-11-28 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PLF-RPT-0004 | Pipeline Material Selection Report | PLF | Issued | -- | -- | 0 | 0 |