Total Documents

242

Tracked in MDR

Timeline Duration

99 days

Total span

Earliest Start

2025-10-06

Dataset baseline

Latest Finish

2026-01-12

Projected completion

Schedule Items

7 tasks displayed

Categories tracked: 18
ID Name Category Status Start Finish Duration (d) Budgeted Units Actions
ARLNG-019-FEL2-PBO-1002-PSM-LYT-0005 Hazardous area classification layout (Compressor Station) PSM Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1032-PSM-LYT-0004 Hazardous area classification layout (Central Hub) PSM Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-PSM-LYT-0003 Hazardous area classification layout (BVS, scraper trap stations) PSM Not issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1002-PSM-LYT-0002 Firefighting Layout - network and equipment (Compressor Station) PSM Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1032-PSM-LYT-0001 Firefighting Layout - network and equipment (Central Hub) PSM Issued 2025-12-19 2025-12-19 1 0
ARLNG-019-FEL2-PBO-1000-PSM-HAZ-0001 HAZID PSM Issued 2025-11-28 2025-11-28 1 0
ARLNG-019-FEL2-PBO-1000-PSM-RPT-0001 EAC + ACR PSM Not issued 2025-12-19 2025-12-19 1 0