Total Documents

242

Tracked in MDR

Timeline Duration

99 days

Total span

Earliest Start

2025-10-06

Dataset baseline

Latest Finish

2026-01-12

Projected completion

Schedule Items

4 tasks displayed

Categories tracked: 18
ID Name Category Status Start Finish Duration (d) Budgeted Units Actions
ARLNG-019-FEL2-PBO-1000-STA-SPC-0001 Specification for Scraper Trap STA Issued 2025-11-14 2025-11-14 1 0
ARLNG-019-FEL2-PBO-1002-STA-MRE-0001 Material Requisition for GAS SRUBBERS (Compressor Station) STA Issued 2025-12-05 2025-12-05 1 0
ARLNG-019-FEL2-PBO-1032-STA-MRE-0001 Material Requisition for STORAGE TANKS (Central Hub) STA Issued 2025-12-05 2025-12-05 1 0
ARLNG-019-FEL2-PBO-1000-STA-MRE-0001 Material Requisition for Pig Traps STA Issued 2025-11-28 2025-11-28 1 0