Total Documents
242
Tracked in MDR
Timeline Duration
99 days
Total span
Earliest Start
2025-10-06
Dataset baseline
Latest Finish
2026-01-12
Projected completion
All Disciplines
242
Architectural (ARC)
6
Commissioning (CMM)
1
Construction (CON)
3
Civil (CVS)
10
Electrical (ELE)
7
HSSE (Health, Safety, Security and Environment) (HSE)
2
INS
6
Piping (PIP)
5
Pipelines and Flow lines (PLF)
135
Project Planning (PLG)
3
Project Management (PMG)
7
PMT
7
Process (PRO)
29
Process Safety Management (PSM)
7
Quality Assurance & Control (QAC)
1
Mechanical Rotating (ROT)
7
Mechanical Static (STA)
4
Structural (STC)
2
Issued ยท 5
Schedule Items
5 tasks displayed
Categories tracked: 18
| ID | Name | Category | Status | Start | Finish | Duration (d) | Budgeted Units | Actions |
|---|---|---|---|---|---|---|---|---|
| ARLNG-019-FEL2-PBO-1002-PIP-LYT-0003 | Overall Plot Plan (Compressor Stations) | PIP | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1032-PIP-LYT-0002 | Overall Plot Plan (Central Hub) | PIP | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PIP-LYT-0001 | Overall Plot Plan (BVS, scraper trap stations) | PIP | Issued | 2025-11-14 | 2025-11-14 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PIP-RPT-0001 | Summary of the pipe classes of the project. | PIP | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 | |
| ARLNG-019-FEL2-PBO-1000-PIP-TDS-0001 | Simplified Data Sheet for Manual Valves | PIP | Issued | 2025-12-05 | 2025-12-05 | 1 | 0 |